On Mar 24, 2008, at 3:58 PM, Wanrong Lin wrote:

Hi,

With a test task as following:

* TODO A test
SCHEDULED: <2008-03-24 Mon ++1w>

If on the scheduled day (today) I do a "C-c C-t" trying to mark it "DONE", the scheduled time does not jump to the next occurrence. However, If I change the task to

* TODO A test
SCHEDULED: <2008-03-23 Sun ++1w>

and do the same thing (note I am "past due" now), things work without a problem.

I am using 5.23a and Emacs 22.1 on Windows.

Thanks a lot for looking into this.

Wanrong